9/2011 |
Strategic Plan adopted by Board of Education (BOE) |
7/2013 |
School conditions assessed |
10/2013 |
Elementary Facilities Plan approved by BOE |
12/2013 |
Master Plan presented to Town Council by BOE |
6/2016 |
Educational Specifications developed |
8/2016 |
Early Site Services completed |
9/2016 |
Refreshed ten-year timeline approved by BOE |
10/2016 |
Educational Specifications approved by BOE |
10/2016 |
Phase Two project budgets approved by BOE |
3/2017 |
Referendum passed by South Windsor residents |
3/2017 |
Public Building Commission (PBC) appointed by Town Council |
6/2017 |
Phase Two School Construction Grant (SCG) applications filed with state |
7/2017 |
Architect selected by PBC |
7/2017 |
Owner's Representative selected by PBC |
8/2017 |
Education programming meetings held |
10/2017 |
Construction Manager selected by PBC |
11/2017 |
Commissioning Agent selected by PBC |
12/2017 |
Community information session held |
1/2018 |
Schematic Design documents approved by PBC |
1/2018 |
Swing space transition meeting held with PRS families |
5/2018 |
SCG applications approved by the state |
6/2018 |
Design Development documents approved by PBC |
7/2018 |
PRS faculty and staff relocated to swing space |
9/2018 |
Community information session held |
9/2018 |
Meeting held with Eli Terry parents |
9/2018 |
Inland Wetlands Agency/Conservation Commission approvals |
9/2018 |
Planning and Zoning Commission approvals |
11/2018 |
BOE approves revised Ed Specs |
12/2018 |
Third Party Code Reviewers approved by PBC |
1/2019 |
Final Plans, Specifications and Cost Estimates approved by PBC and BOE |
1/2019 |
Philip R. Smith Groundbreaking |
2/2019 |
Final Plans approved by the state |
|
|
|
|